Resource · Tool
TN compliance calendar
Every filing, approval and registration tracked in our own register, for a Tamil Nadu industrial facility. Filter by domain and authority. A dash means the source data doesn't say. That is not the same as “no timeline exists.”
Showing 128 of 128
Change of land use (planned areas)
Statutory
Development permission (non-planned areas)
No state timeline
Collector concurrence for development on wet land
Statutory
Layout approval
Statutory
Planning permission and building permit
Statutory
Plinth level inspection
Statutory
Last storey inspection
Statutory
Completion certificate
Statutory
Non-forest land certificate / distance-from-forest letter
Statutory
NOC for construction near a protected monument
Statutory
Coastal Regulation Zone Clearance
No state timeline
Hill Area Conservation Authority clearances
No state timeline
NOC - Railways
No state timeline
NOC - Civil Aviation / Air Force
No state timeline
NOC - Chennai Metro Rail
No state timeline
NOC - power line buffer
No state timeline
NOC for building plan and installation (public health)
Statutory
Land allotment in a government industrial estate
Statutory
Property registration and encumbrance certificate
Statutory
Environmental Clearance
No state timeline
Consent to Establish - Water
Statutory
Consent to Establish - Air
Statutory
Consent to Operate - Water and Air
Statutory
Hazardous and other wastes authorisation
Statutory
Bio-medical waste authorisation
Statutory
Solid waste management authorisation
Statutory
Construction and demolition waste authorisation
Statutory
Plastic waste registration
Statutory
E-waste authorisation (manufacturer)
Statutory
Battery waste EPR registration
No state timeline
Water cess assessment and returns
No state timeline
Groundwater extraction clearance
No state timeline
Factory plan approval
Statutory
Factory registration and licence
Statutory
Notice of change of manager
No state timeline
Pressure vessel testing or examination
No state timeline
Site appraisal and major accident hazard notification
No state timeline
Safety officer, safety committee and on-site emergency plan
No state timeline
BOCW establishment registration
Statutory
Fire NOC - non-multi-storeyed building
Statutory
Fire NOC - multi-storeyed building
Statutory
Fire licence - non-multi-storeyed building
Statutory
Fire licence - multi-storeyed building
Statutory
NOC - cracker shop or cracker cluster shop
Statutory
Statutory approval of electrical drawings
Statutory
Additions or alterations to approved drawings
Statutory
Electrical safety certificate
Statutory
Revalidation or additions to safety certificate
Statutory
DG set installation registration
Statutory
Permission to erect lift; licence to work lift; renewal
Statutory
Electricity tax exemption
Statutory
Approval of boiler design and manufacturing drawings
Statutory
Provisional registration of boiler
Statutory
Final registration of boiler
Statutory
Renewal of boiler registration
Statutory
Registration and certification of steam pipeline
Statutory
Permission for repair or alteration to boiler
Statutory
Transfer of boiler ownership
Statutory
Self-certification of boilers through boiler engineers
Statutory
Classification and exemption reference (not an approval)
-
Licence to import and store petroleum Class A up to 300 L (Form XII)
No state timeline
Licence to import and store petroleum Class B up to 25,000 L (Form XIII)
No state timeline
No Objection Certificate under Rule 144
No state timeline
Licence to store petroleum in tanks with pump outfit for fuelling motor conveyances (Form XIV)
No state timeline
Licence to import and store petroleum in an installation (Form XV)
No state timeline
Licence to import and store petroleum otherwise than in bulk (Form XVI)
No state timeline
Prior intimation for storage of petroleum Class C up to 45,000 L
No state timeline
Licence to carry petroleum by land on mechanically propelled vehicles (Form XI)
No state timeline
Licence to transport Class A or B in bulk for on-site refuelling (Form XIX)
No state timeline
Tank test certificate
No state timeline
Certificate of safety
No state timeline
Approval of Ex electrical apparatus
No state timeline
Pipeline laying approval and commissioning permission
No state timeline
Storage of LPG, propane or flammable gas in pressure vessels
No state timeline
Gas cylinder filling and storage licence
No state timeline
Explosives licence
No state timeline
Ammonium nitrate licence
No state timeline
Calcium carbide licence
No state timeline
NOC for retail outlet - establishment, storage and sale of petroleum
Statutory
Permanent licence for sale of crackers
Statutory
Mine opening notice, statutory appointments, mine plan approval and regulation permissions
No state timeline
Mining or quarry lease and mineral concession
No state timeline
HT new power connection
Statutory
LT new power connection
Statutory
HT or LT load addition or reduction
Statutory
Temporary power connection
Statutory
Solar rooftop empanelment
Statutory
Water connection for industries
Statutory
New water connection for industries and institutions
Statutory
Water or sewer connection for commercial establishments
Statutory
Road cutting permission
Statutory
Principal employer registration - contract labour
Statutory
Contractor licence - contract labour
Statutory
Principal employer registration - inter-state migrant workmen
Statutory
Contractor licence - inter-state migrant workmen
Statutory
Shops and Establishments registration
Statutory
Motor Transport Workers registration
Statutory
Catering establishment registration
Statutory
EPF registration
No state timeline
ESI registration
No state timeline
Professional tax assessment number
Statutory
Certification of standing orders
No state timeline
Statutory registers, returns and displays
No state timeline
Industry Licence
Statutory
Trade Licence
Statutory
Dangerous and Offensive trades licence
No state timeline
Property tax and company tax assessment
Statutory
Telecom infrastructure installation permission
Statutory
FSSAI licence or registration
Statutory
Drug manufacturing licence; loan licence; test licence
Statutory
WHO-GMP certificate and additional product endorsement
Statutory
Legal Metrology manufacturer, dealer or repairer licence
Statutory
Packer and importer registration
Statutory
Verification and stamping of weights and measures
Statutory
Insecticide manufacturing licence
Statutory
Excise permits and FL licences
Statutory
BIS licence or CRS registration
No state timeline
Narcotics and psychotropic substances licences
No state timeline
GST registration
Statutory
Udyam registration, IEC and incentive claims
Statutory
Major Accident Hazard (MAH) unit notification / registration
No state timeline
On-site Emergency Plan
No state timeline
Off-site Emergency Plan
No state timeline
Nucleonic gauge / radioactive source licence
No state timeline
Dock safety approval
No state timeline
Importer-Exporter Code (IEC)
No state timeline
Export Promotion Capital Goods (EPCG) Authorisation
No state timeline
District Disaster Management Plan coordination
-