An industrial project is rarely governed by one approval or one department. Its regulatory requirements emerge from the proposed location, land status, building, manufacturing process, machinery, utilities, workforce, emissions, waste and materials stored at the facility.

AequiRadix examines these factors together and develops a project-wide regulatory map: what is required, what is conditional, what is not presently attracted and what must be resolved before the project proceeds.

What is regulatory mapping?

Regulatory mapping begins with the facts of the proposed project, not a standard list of departmental approvals. The site, activity, process, capacity, building configuration, utilities, workforce and material inventories are examined against the applicable regulatory framework.

Each requirement is then placed within the project's actual sequence. The map identifies the statutory basis, responsible authority, relevant project stage, dependencies, unresolved questions and action needed to move forward.

Illustrative project

Precision-engineering facility in Tamil Nadu

Illustrative project, not an assessment of an actual facility.

The sample below concerns a proposed precision-engineering and electric-vehicle components facility on a leased plot within an approved SIPCOT industrial layout.

Illustrative project assumptions
Project factorIllustrative assumption
FacilityNew precision-engineering and EV-components manufacturing unit
BuildingApproximately 6,500 sq. m comprising a non-multi-storeyed production building, warehouse, utilities and office
OperationsCNC machining, aqueous surface preparation, powder coating and mechanical assembly
WorkforceApproximately 180 workers at full operation
UtilitiesHT electricity supply, transformer and standby diesel generator; diesel-storage arrangement not yet finalised
Water and wastewaterIndustrial-park water supply; process wastewater and domestic sewage to be treated; no groundwater abstraction proposed
WasteUsed oil, treatment sludge and process residues expected
MaterialsFinal chemical register, safety data sheets and maximum inventories not yet available
Excluded activitiesNo foundry, electroplating, heat treatment, chemical manufacture, boiler, bulk gas vessel, explosives or radioactive source
Land assumptionProposed activity assumed to be consistent with the allotment terms, approved industrial layout and applicable industrial-park conditions, subject to document verification

Sample regulatory map

Definite means that the requirement is attracted on the stated assumptions. Conditional means that applicability or the precise approval route depends on information still to be confirmed. Not presently identified means that the requirement does not appear to arise from the illustrative facts but must be reconsidered if those facts change.

Sample regulatory mapping matrix for the illustrative precision-engineering facility
Regulatory requirementApplicabilityAuthorityProject stageKey dependency or required action
Land allotment and permitted industrial activity
Definite
SIPCOTSite confirmation and design

Review the lease or allotment order, approved layout, plot conditions, permissible activity and industrial-park environmental conditions. Confirm that the proposed machining and coating operations fall within the allotted activity.

SIPCOT Citizens Charter
Land use, planning permission and building permit
Definite
Competent planning authority and local bodyBefore construction

Verify survey boundaries and approved industrial land use. Coordinate the site plan, access, setbacks, parking, utility areas, fire provisions and process layout. Planning permission and the local building permit must be separately identified for the project's location.

Planning permission procedure (PE_6)
Prior environmental clearance
Not presently identified
MoEFCC or SEIAA, if attractedBefore site preparation or construction

The assumed manufacturing activity is not presently identified as a scheduled project under the EIA framework. This conclusion must be rechecked against the final process, production capacity, built-up area, site sensitivities, amendments to the EIA Notification and the industrial park's environmental clearance.

EIA Notification, 2006
TNPCB Consent to Establish and Consent to Operate
Definite
Tamil Nadu Pollution Control BoardEstablishment and pre-operation

Finalise the product and capacity, process flow, water balance, emission sources, effluent and sewage treatment, waste streams and plant layout. CTE must inform the establishment of the unit, while CTO must be addressed before operation in accordance with the consent framework and applicable conditions.

TNPCB consent information
Factory plan approval and operative registration or licensing process
Definite

Definite in substance; procedural route requires confirmation

Directorate of Industrial Safety and Health, Tamil NaduDesign and pre-operation

Manufacturing with power and the proposed workforce clearly engages the factory-safety regime. The OSH Code commenced centrally on 21 November 2025, while current Tamil Nadu DISH materials continue to provide factory plan-approval and registration or licensing services. The operative State forms, rules and transitional procedure must therefore be verified when the project is taken up.

OSH Code commencement (S.O. 5321(E))
Fire NOC, fire-safety compliance and operational fire licence
Conditional

Conditional as to the precise route

Tamil Nadu Fire and Rescue Services and the building authorityDesign and pre-operation

Confirm building height, occupancy, fire load, process hazards, storage and final layout. The present assumptions indicate the non-multi-storeyed route, under which the State procedure distinguishes a pre-establishment NOC from the pre-operational fire licence and links the latter to the approved building plan.

Non-multi-storeyed fire NOC (PE_9)
HT supply and electrical installation approvals
Definite

Definite if the proposed HT installation proceeds

TANGEDCO and Tamil Nadu Electrical InspectorateDesign and pre-energisation

Obtain the applicable load sanction and electrical drawing approval, then complete the safety-certification process before energisation. Transformer, generator, switchgear and earthing arrangements must align with the approved project layout.

Electrical drawing approval (PE_13)
Water supply, effluent and sewage arrangements
Definite
SIPCOT or relevant supplier and TNPCBDesign, establishment and operation

Confirm the authorised water source, sanctioned quantity, connection conditions, segregation of wastewater, treatment capacity and disposal or reuse route. No groundwater approval is presently mapped because the example assumes that groundwater will not be abstracted.

Hazardous and other waste authorisation
Conditional

Conditional on waste classification; likely applicable

Tamil Nadu Pollution Control BoardBefore handling waste and during operation

Characterise the used oil, treatment sludge and process residues under the applicable waste rules. Confirm quantities, on-site storage, authorised transport and disposal or recovery routes, and align the authorisation with the consent conditions.

TNPCB hazardous-waste authorisation
Diesel and petroleum storage
Conditional
PESO or another competent authority, depending on the final installationBefore procurement and installation

Freeze the fuel classification, maximum inventory, tank type, location and dispensing arrangement. The required approval or licence cannot be determined responsibly until the final storage configuration and quantity are known.

PESO petroleum storage licensing guidance
Hazardous-chemical and major-accident requirements
Conditional
Authorities designated under the environmental and industrial-safety frameworkDesign and operation

Compile the chemical register, safety data sheets and maximum inventories. Each substance and quantity must then be tested against the MSIHC Rules; the presence of chemicals alone does not establish that every requirement under those Rules applies.

MSIHC Rules, 1989
Pre-operational closure and continuing compliance
Definite
TNPCB, DISH, TNFRS, Electrical Inspectorate, SIPCOT and other authorities as applicableBefore operation and throughout the facility's life

Confirm that the as-built facility matches its approved plans and conditions; close the relevant consent, factory, fire, electrical, storage and waste requirements; and establish a compliance calendar for monitoring, records, returns, validity management and regulatory change control. Hazardous-waste records and annual returns are among the continuing requirements where the waste rules apply.

TNPCB hazardous-waste authorisation
Land allotment and permitted industrial activityDefinite
Applicability
Definite
Authority
SIPCOT
Project stage
Site confirmation and design
Key dependency or required action

Review the lease or allotment order, approved layout, plot conditions, permissible activity and industrial-park environmental conditions. Confirm that the proposed machining and coating operations fall within the allotted activity.

SIPCOT Citizens Charter
Land use, planning permission and building permitDefinite
Applicability
Definite
Authority
Competent planning authority and local body
Project stage
Before construction
Key dependency or required action

Verify survey boundaries and approved industrial land use. Coordinate the site plan, access, setbacks, parking, utility areas, fire provisions and process layout. Planning permission and the local building permit must be separately identified for the project's location.

Planning permission procedure (PE_6)
Prior environmental clearanceNot presently identified
Applicability
Not presently identified
Authority
MoEFCC or SEIAA, if attracted
Project stage
Before site preparation or construction
Key dependency or required action

The assumed manufacturing activity is not presently identified as a scheduled project under the EIA framework. This conclusion must be rechecked against the final process, production capacity, built-up area, site sensitivities, amendments to the EIA Notification and the industrial park's environmental clearance.

EIA Notification, 2006
TNPCB Consent to Establish and Consent to OperateDefinite
Applicability
Definite
Authority
Tamil Nadu Pollution Control Board
Project stage
Establishment and pre-operation
Key dependency or required action

Finalise the product and capacity, process flow, water balance, emission sources, effluent and sewage treatment, waste streams and plant layout. CTE must inform the establishment of the unit, while CTO must be addressed before operation in accordance with the consent framework and applicable conditions.

TNPCB consent information
Factory plan approval and operative registration or licensing processDefinite
Applicability
Definite in substance; procedural route requires confirmation
Authority
Directorate of Industrial Safety and Health, Tamil Nadu
Project stage
Design and pre-operation
Key dependency or required action

Manufacturing with power and the proposed workforce clearly engages the factory-safety regime. The OSH Code commenced centrally on 21 November 2025, while current Tamil Nadu DISH materials continue to provide factory plan-approval and registration or licensing services. The operative State forms, rules and transitional procedure must therefore be verified when the project is taken up.

OSH Code commencement (S.O. 5321(E))
Fire NOC, fire-safety compliance and operational fire licenceConditional
Applicability
Conditional as to the precise route
Authority
Tamil Nadu Fire and Rescue Services and the building authority
Project stage
Design and pre-operation
Key dependency or required action

Confirm building height, occupancy, fire load, process hazards, storage and final layout. The present assumptions indicate the non-multi-storeyed route, under which the State procedure distinguishes a pre-establishment NOC from the pre-operational fire licence and links the latter to the approved building plan.

Non-multi-storeyed fire NOC (PE_9)
HT supply and electrical installation approvalsDefinite
Applicability
Definite if the proposed HT installation proceeds
Authority
TANGEDCO and Tamil Nadu Electrical Inspectorate
Project stage
Design and pre-energisation
Key dependency or required action

Obtain the applicable load sanction and electrical drawing approval, then complete the safety-certification process before energisation. Transformer, generator, switchgear and earthing arrangements must align with the approved project layout.

Electrical drawing approval (PE_13)
Water supply, effluent and sewage arrangementsDefinite
Applicability
Definite
Authority
SIPCOT or relevant supplier and TNPCB
Project stage
Design, establishment and operation
Key dependency or required action

Confirm the authorised water source, sanctioned quantity, connection conditions, segregation of wastewater, treatment capacity and disposal or reuse route. No groundwater approval is presently mapped because the example assumes that groundwater will not be abstracted.

Hazardous and other waste authorisationConditional
Applicability
Conditional on waste classification; likely applicable
Authority
Tamil Nadu Pollution Control Board
Project stage
Before handling waste and during operation
Key dependency or required action

Characterise the used oil, treatment sludge and process residues under the applicable waste rules. Confirm quantities, on-site storage, authorised transport and disposal or recovery routes, and align the authorisation with the consent conditions.

TNPCB hazardous-waste authorisation
Diesel and petroleum storageConditional
Applicability
Conditional
Authority
PESO or another competent authority, depending on the final installation
Project stage
Before procurement and installation
Key dependency or required action

Freeze the fuel classification, maximum inventory, tank type, location and dispensing arrangement. The required approval or licence cannot be determined responsibly until the final storage configuration and quantity are known.

PESO petroleum storage licensing guidance
Hazardous-chemical and major-accident requirementsConditional
Applicability
Conditional
Authority
Authorities designated under the environmental and industrial-safety framework
Project stage
Design and operation
Key dependency or required action

Compile the chemical register, safety data sheets and maximum inventories. Each substance and quantity must then be tested against the MSIHC Rules; the presence of chemicals alone does not establish that every requirement under those Rules applies.

MSIHC Rules, 1989
Pre-operational closure and continuing complianceDefinite
Applicability
Definite
Authority
TNPCB, DISH, TNFRS, Electrical Inspectorate, SIPCOT and other authorities as applicable
Project stage
Before operation and throughout the facility's life
Key dependency or required action

Confirm that the as-built facility matches its approved plans and conditions; close the relevant consent, factory, fire, electrical, storage and waste requirements; and establish a compliance calendar for monitoring, records, returns, validity management and regulatory change control. Hazardous-waste records and annual returns are among the continuing requirements where the waste rules apply.

TNPCB hazardous-waste authorisation

The project's building-completion position must also be checked against the version of the Tamil Nadu Combined Development and Building Rules and the competent authority's procedure applicable at the time. The Rules distinguish industrial buildings from the buildings generally required to obtain a completion certificate, but this does not remove the need to comply with the approved plan or satisfy separate factory, fire, electrical and pollution-control requirements. Tamil Nadu online planning portal.

How requirements connect

Regulatory work does not always proceed as a single line of applications. Land status and the permitted activity shape the initial project definition; planning, building and environmental assessments may then proceed as parallel workstreams, each using the same underlying project facts.

Technical approvals for electrical installations, fire protection, factory safety and specialised storage depend on the developing design. Before operation, the project must close the requirements that apply to the completed facility. The resulting approvals and their conditions then become part of the facility's continuing compliance system.

  1. Site and activity

    Land status and the permitted activity shape the initial project definition.

  2. Parallel workstreams

    Planning, building and environmental assessments may proceed together, using the same project facts.

  3. Technical approvals

    Electrical, fire, factory safety and specialised storage follow the developing design.

  4. Pre-operation and life

    Close the requirements that apply to the completed facility, then keep the compliance system current.

The actual sequence is project-specific. A change in process, capacity, building layout, utility, workforce or material inventory can alter an earlier applicability decision and require the regulatory map to be revisited.

What the client receives

AequiRadix provides a project-specific regulatory map setting out:

  • The project facts and documents reviewed
  • Definite, conditional and presently non-applicable requirements
  • The statutory and procedural basis for each conclusion
  • The responsible authority and relevant project stage
  • Dependencies between design decisions and approval processes
  • Missing information and matters requiring authority confirmation
  • Recommended actions, sequencing and responsibility allocation
  • Continuing obligations and circumstances that require the map to be updated

The result is a working document for promoters, designers, consultants and operating teams, not merely a list of licences.

Map the project before regulatory assumptions become project constraints.

Share the proposed location, activity, process, capacity and present project stage. AequiRadix will assess the appropriate scope for mapping the project's approvals, licences and continuing regulatory obligations.

Request an Approvals Map

Regulatory conclusions depend on verified project facts and the law and administrative practice in force at the time of review.

Enquiry · Regulatory Mapping

Tell us about your proposed project or facility.

A brief outline is enough to begin. We will review your enquiry and get in touch to understand the requirement.

Submitted information will be used only to respond to this enquiry. It is not used for marketing lists.